Jul 6, 2020
The covid-19 pandemic brought a pause to the drilling operations in Tulu Moye that had started in the first week of March 2020. After monitoring the covid situation in Ethiopia and having health and safety measures ready for the upcoming situation, Reykjavík...
Jun 25, 2020
Corbetti Geothermal PLC is developing a geothermal power project in the Corbetti caldera in Ethiopia. Reykjavik Geothermal (RG) along with Berkeley Energy (BE), are the principal participants in the project. Reykjavik Geothermal is pleased to announce this...
Jun 16, 2020
May 22, 2020 marked a monumental shift for the geothermal sector of Ethiopia. The cabinet of Ethiopia, known as the Council of Ministers, came into agreement to send the Geothermal Proclamation Amendment to the Federal Parliamentary Assembly of Ethiopia for review....
Jun 10, 2020
Reykjavík Geothermal’s Abaya and Tulu Moye concessions have up until now been covered by the same exploration license. The Abaya concession is located in the SNNPR (Southern Nations and Nationalities People’s Region) region, and Tulu Moye in the Oromia...
Apr 21, 2020
The Tulu Moye Geothermal Project has been granted a $10 million concessional senior loan from the Clean Technology Fund. This loan will go towards the development of the first phase of the project – a 50 MW geothermal power plant. Ultimately, the project will...
Mar 13, 2020
March 4, 2020 marked the commencement of exploration drilling for the Tulu Moye Geothermal Project where three exploration wells will be drilled in the project area located in the Oromia Region, Ethiopia. This long-awaited milestone was spearheaded by the independent...